Shiloh

Building in the woods – out where the wild things are . .

Hey there! Thanks for dropping by Shiloh! Take a look around
and grab the RSS feed to stay updated. See you around!

Digging a hole in the ground

This week will hopefully mark another milestone in the home building project. Earlier today I called the company we selected to dig our foundation and asked if they could begin work later this week. It looks like they might begin Friday or Saturday.

If this happens we will only be three weeks behind for this part of the project :)

Around the same time we finished peeling the logs Rachel and I decided to make some changes in the house plans. The major change was that we decided to extend the length of the walls from 26′ to 31′. It will increase the heated and cooled living area from something like 1200 sq. ft to just over 1700 sq. ft. Unfortunately it required an update of the interior and structural drawings.

Even so, the interior drawings are now complete and the structural plans will be done in the next day or so. Once these are done the building permit can be updated with the changes.

To make things simpler and allow us to as much of the work as possible we are using what are called “pier blocks”. These are essentially pyramidal constructs with flat tops. We are using a total of 17 pier blocks. They will be arranged around the edge of the structure to hold the logs with more inside the square to support the flooring and what are called ridge pole support logs and the girder support log. As with the interior and structural drawing updates, the increase in size of the house has meant that we have to increase the size of some of the pier blocks so some additional work was necessary.

The contractor and crew will come out with a bobcat and an excavator and dig the seventeen holes for the form. These holes must be accurately place and once the forms are placed they must be absolutely level and at the same height above grade (ground) as the other forms. In our case the top of each form will be 18 inches above grade. The bottom of the form will be 18 inches below grade for a total height of 3′ for the form. Once the form is in place and level the hole will be backfilled so that the form don’t “float up” when the concrete is poured. Even though the forms are heavy, it is possible for the concrete to push the form up or even blow the sides of the form out if the seams are not reinforced enough. This will create a huge problem in either case. We reinforced our forms with two by fours and brackets to keep this from happening.

We began building our forms quite some time ago. Along the way we managed to make some mistakes and learn a thing or two. When we finish nailing the last one together this week it will get us one step closer to living in our home!

Cutting a form:

The day we were cutting the majority of the forms it was only slightly above freezing for much of the day.

We also laid out the area where the foundation is going to be located. While it might not look like much in the picture below, the square marked out by the string is the exact area of the house down to the inch.  In fact, the front door be within a foot or two of the end of small pine log you can see “pointing” towards the foundation area. The kitchen will be to the right of the front door and the great room will be what you enter first.

A log home weighs a great deal. A single dry log is going to weigh something like 1,000 pounds.  It is important to have a solid, firm foundation or later we will have difficulties. While it has been a challenge to build the proper forms and it will be some hard work to place them correctly, in the end it will worth it knowing we won’t have issues with the foundation of the house.


 

You can leave a response, or trackback from your own site.

Leave a Reply